Location/facility |
State electorate |
Scope of works |
Funding source |
Status |
Far North |
Weipa, Evans Landing |
Cook |
Upgrade pontoon to attenuate wave action |
MIIP |
Off‑site fabrication has commenced on the Sunshine Coast. On‑site works scheduled for first half of 2021. |
Newell Beach |
Cook |
New 2-lane boat ramp and floating walkway |
MIF |
Design amendments underway. Tender process to commence once approvals gained. |
Yorkeys Knob new boat ramp |
Barron River |
Single 6-lane boat ramp with 2 floating walkways |
MIF |
Deed of agreement executed November 2019. Land and easement resumption process continuing. The federal Environment Protection and Biodiversity Conservation Act (EPBC) approvals process is underway. |
Palm Cove |
Barron River |
Major jetty maintenance |
MIIP |
Works scheduled for after wet season – April to June 2021. |
Bramston Beach, Joyce Creek |
Mulgrave |
Relocate boat ramp |
MIF |
Fabrication of raised walkway completed in December 2020. Contractor to re-establish to site to complete installation of raised walkway including construction of reinforced concrete abutment in January/February 2021. |
Mission Beach Clump Point |
Hill |
Widen boat ramp, additional floating walkway, upgrade breakwater, new detached breakwater, jetty, and pontoons |
DSD/MIIP |
Project works complete. Cassowary Coast Regional Council and MSQ project teams working on facility operational management plan and commercial user agreements. |
Coconuts, Fern Street |
Hill |
Resurfacing and extension of boat ramp |
MIF/MIIP |
Preliminary design completed and marine park application submitted in December 2020. Tendering to commence in January 2021. Works scheduled for March to June 2021. |
Mackay / Whitsunday |
Molongle Beach Road, Molongle Creek
Deed of agreement |
Burdekin |
Entrance channel deepening |
MIIP |
Disposal facility: Disposal facility construction underway. Bunds are complete. Wet season rainfall may delay completion of the works. Construction of weir boxes to be completed and installation of hydro-mulching to commence in January.
Dredging: Dredging approvals awaiting change of lot boundary by WRC, expected to occur late-January 2021. Expect approvals application to be re-submitted for dredging works once lot boundary change is confirmed. |
Midge Point |
Whitsunday |
New boat ramp |
MIF |
Great Barrier Reef Marine Parks Authority permit received 18 September 2020. Land survey completed and road realignment lodged with Department of Resources by Mackay Regional Council. Approvals from DES and DAF state agencies anticipated March 2021. Tenders invitation to follow. Construction scheduled May to November 2021. |
Slade Point, Mackay |
Mackay |
New boat ramp |
MIIP |
$1 million grant contribution by TMR to Mackay Regional Council project. Works expected mid-2021 (council delivering). |
Mackay Harbour |
Mackay |
Replace modules on northern floating walkway |
MIIP |
Design completed in December 2020. Modules to be fabricated in January 2021. |
Shute Harbour |
Whitsunday |
Improvements to recreational boat launching infrastructure |
MIF |
Contractor has submitted construction plan including insurances, test plans, program, Environmental Management Plan and Site Management Plan. Contractor commenced procurement of materials for the works in December 2020. Contractor expected to establish to site in mid-February 2021. |
Mackay, River Street |
Mackay |
Safety improvements to boat ramp |
MIIP |
Civil works (revetment) completed in December 2020. Pontoon modules extension expected to commence late January 2021. |
Fitzroy |
Casuarina Creek (off Bajool-Port Alma Road) |
Mirani |
New 2-lane boat ramp with a floating walkway at Casuarina Creek. |
MIF |
Rockhampton Regional Council (RRC)progressing changes to land tenure. Revised concept configuration including minor location shift ready to progress once land tenure issues are resolved. |
Inkerman Creek (off Bajool-Port Alma Road) |
Mirani |
New single-lane boat ramp at Inkerman Creek |
MIF |
Designs to be amended in January. |
Thompson Point |
Keppel |
New 2-lane boat ramp plus floating walkway |
MIF |
Boat ramp construction in progress. Floating walkway piles completed in December. Floating walkaway modules manufacture in progress. Approvals for the proposed location of the barge ramp to be obtained in January. |
Corbetts Landing |
Keppel |
New boat ramp and floating walkway |
MIF |
Boat ramp construction in progress. |
Rosslyn Bay Boat Harbour |
Keppel |
Reconfigure boat ramps and floating walkways |
MIF |
Planning commenced. |
North Coast |
Golden Beach |
Caloundra |
Ramp resurface |
MIIP |
Tenders were invited in December 2020, to be evaluated and awarded in January 2021. |
Metropolitan |
Victoria Point, Colburn Avenue |
Redlands |
Dredging the channel to the northern ramp |
MIIP |
Dredging in progress. |
Dunwich, Junner Street jetty |
Oodgeroo |
Unsafe jetty demolition |
MIIP |
Tidal works approvals being obtained. Works to commence on receipt of works approvals early 2021. |
Southern Moreton Bay Island |
Redlands |
Four new ferry pontoon terminals |
TransLink and RCC |
Tenders assessment continues. |
Wellington Point access channel |
Oodgeroo |
Maintenance dredging |
MIIP |
Pre-lodgement meetings with approvals agencies scheduled for early 2021. |